The little grey number is smaller numbers in purple used in the Planner view represent the difference between the current value baseline and the requested or approved valuevalues, depending on the column.
If the number is a negative then there is a decrease from the
...
baseline and less full time equivalent has been requested or approved for
...
that team.
If the number is a positive then there is an increase from the
...
baseline and more full time equivalent has been requested or approved for
...
that team.
If
...
N/C
is displayed then there is no change between the
...
baseline and the requested or approved
...
values.
In the example above, the Squad 100 currently has a baseline of 9.8 FTE. It’s requested an increase up to 18.8 FTE, hence the delta number for that columns shows +9
. This request hasn’t (yet) been approved, hence the delta number for that column shows N/C
.
Related articles
Filter by label (Content by label) | ||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
...