Ideally, execute this process outside of regular business hours

There are 4 key steps that must be executed in the order specified below

1

Confirm you’re in the correct workspace

2

Go to Allocations (in Settings → Data integrations).

image-20240205-034109.png
3

Set baseline date to latest index

you will need to refresh the page for the index to show up in the date picker. a page refresh reloads the required config

menu: Data Integrations → Allocations → [Active Project] →Edit )→ Baseline date set, else will use the last date set (In other words, set this to the current date) → Update

Note: The date box must yellow to ensure that you have the latest worker file.

image-20240205-034840.png

4

Run recalculate baseline

active allocation project → click on recalculate allocated baseline button (another window will pop up, just confirm by clicking ‘OK’).

An import will start. Once it finishes (wait for import success - might take a while).

5

Check that recalculation worked

  • Numbers on the supply side and Planner should match.

  • Numbers on the demand side and Forecast should match.

Checking recalculation.jpg