A baseline is a snapshot view of all people and teams at a point of time, to be used during the planning process.
The baseline includes:
Who was allocated to which demand team.
What supply team the members came from.
Let’s take an example of demand team Squad A
, on Jan 1st when we hit the 'calculate baseline' button, there were:
1 x PO
1 x BA
3 x Engineers
On Jan 5th, one of the Engineers left the team. In Directory we will see in real time that the team FTE is now reduced to 4 but when we go into Planner, the baseline will still state 5 FTE. This is because the baseline holds the snapshot of the team composition as of Jan 1st.
The baseline will be updated to reflect these changes only if we recalculate baseline.