How to execute calculation of baseline
Ideally, execute this process outside of regular business hours
There are 4 key steps that must be executed in the order specified below
The following actions can only be done by a System Admin
user
1 | Start from the TeamForm website On the top left part of the site, under the TeamForm icon. Click on the down arrow to select the specific | |
2 | Go to Allocations (in Settings → Data integrations).
| |
3 | Set baseline date to latest index you will need to refresh the page for the index to show up in the date picker. a page refresh reloads the required config menu: Data Integrations → Allocations → [Active Project] →Edit )→ Baseline date set, else will use the last date set (In other words, set this to the current date) → Update Note: The date box must be yellow to ensure that you have the latest HR people file. |
|
4 | Run recalculate baseline active Planning Period → click on recalculate allocated baseline button (another window will pop up, just confirm by clicking ‘OK’). An import will start. Once it finishes (wait for import success - might take a while).
|
|
5 | Check that recalculation worked
|
|